The slab becomes a reality

6am start, with the cement truck arriving at 7:30.  It may have been drizzling to start, but the day sure cleared up by the end.  Irrespective, a pump truck was used to get the 6.4 m3 of concrete on site. Made the job go very quickly.

So it is in and done.  The expansion joints will be added tomorrow (done by saw, rather than trowel).

It can be walked on tomorrow, and built upon in a week.  Given the shed is a week away on Monday, the timing was getting pretty tight in the end (although there will still have been a few days grace as the erectors won’t be on site the day the shed arrives!  I’ll soon be able to take delivery of the SawStop as well (finally!).