This post was stuck to the top of the blog for the duration of the steps of the shed build, from 1 November through to completion of the shed assembly.
Now that has been completed, it has been unstuck, and won’t be updated further, but have a look at posts around the dates shown for the related posts and progress photos and videos. There were over 40 updates to this timetable as dates kept shifting (normally right). It was a very long process, and I am very glad for it to have finally reached the current status. From here on in progress will only be recorded through the standard blog posts.
Project Stage | Update | Commence | Complete |
Report & Consent | Completed | 5 Sep | 24 Sep |
Building Permit | Completed | 7 Oct | 29 Oct |
Order Shed | Completed | 8 Oct | 8 Oct |
Order Concrete | Completed | 29 Oct | 16 Nov |
Shed Manufacture | Completed | 11 Nov | 28 Nov |
Clear Out & Remove Shed | Completed | 3 Nov | 3 Nov |
Order Skip | Completed | 16 Nov | 16 Nov |
Block Clearance | Completed | 16 Nov | 16 Nov |
Stone, Rebar & Footings | Completed | 19 Nov | 19 Nov |
Building Inspection Footings | Completed | 20 Nov | 20 Nov |
Casting Slab | Completed | 22 Nov | 22 Nov |
Shed Arrival | Completed | 29 Nov | 29 Nov |
Shed Assembly | Completed | 20 Dec | 8 Jan |
Downpipes to stormwater | Completed | 20 Jan | 20 Jan |
Final Building Inspection | Completed | 21 Jan | 21 Jan |
Electrical Installation | Completed | 21 Jan | 22 Jan |
Grand Opening | 2014 |