Shed Timetable

This post was stuck to the top of the blog for the duration of the steps of the shed build, from 1 November through to completion of the shed assembly.

Now that has been completed, it has been unstuck, and won’t be updated further, but have a look at posts around the dates shown for the related posts and progress photos and videos.  There were over 40 updates to this timetable as dates kept shifting (normally right).  It was  a very long process, and I am very glad for it to have finally reached the current status. From here on in progress will only be recorded through the standard blog posts.

Project Stage Update Commence Complete
Report & Consent Completed 5 Sep 24 Sep
Building Permit Completed 7 Oct 29 Oct
Order Shed Completed 8 Oct 8 Oct
Order Concrete Completed 29 Oct 16 Nov
Shed Manufacture Completed 11 Nov 28 Nov
Clear Out & Remove Shed Completed 3 Nov 3 Nov
Order Skip Completed 16 Nov 16 Nov
Block Clearance Completed 16 Nov 16 Nov
Stone, Rebar & Footings Completed 19 Nov 19 Nov
Building Inspection Footings Completed 20 Nov 20 Nov
Casting Slab Completed 22 Nov 22 Nov
Shed Arrival Completed 29 Nov 29 Nov
Shed Assembly Completed 20 Dec 8 Jan
Downpipes to stormwater Completed 20 Jan 20 Jan
Final Building Inspection Completed 21 Jan 21 Jan
Electrical Installation Completed 21 Jan 22 Jan
Grand Opening 2014